321. |
Scheduling is |
A. |
alloting a job to an operator |
B. |
alloting a job to a machine |
C. |
fixing the time of completition of a job |
D. |
detailing the sequence of operation job wise and machine wise |
Answer: Option D
Explanation:
|
322. |
Expediting is watching |
A. |
flow of material |
B. |
worker's activity |
C. |
minimizing delay |
D. |
none of the above |
Answer: Option B
Explanation:
|
323. |
Who proposed that all human efforts can be measured in terms of a common unit partly composed of actual work and partly of compensating relaxation? |
Answer: Option D
Explanation:
|
324. |
Control of production is done through |
A. |
scheduling |
B. |
follow up |
C. |
dispatching |
D. |
none of the above |
Answer: Option B
Explanation:
|
325. |
Break even analysis requires |
A. |
fixed cost |
B. |
variable cost |
C. |
income |
D. |
none of the above |
Answer: Option D
Explanation:
|
326. |
At break-even point, total cost is equal |
A. |
fixed cost |
B. |
variable cost |
C. |
income |
D. |
none of the above |
Answer: Option C
Explanation:
|
327. |
M.T.M. helps in |
A. |
Establishing time standards |
B. |
Estimating cost |
C. |
Improving existing methods |
D. |
Developing methods before the starting of production |
E. |
All of the above |
|
|
Answer: Option E
Explanation:
|
328. |
Dispatching involves |
A. |
starting the work |
B. |
making plan correction |
C. |
collection data |
D. |
none of the above |
Answer: Option A
Explanation:
|