Engineering :: Railway Engineering
|
|
|
|
|
|
| 241. |
The main device used for interlocking is |
| A. |
point lock |
B. |
treadle bar |
| C. |
detector |
D. |
all of these |
Answer: Option D
Explanation:
|
| 242. |
In case of level crossing, the railway track and road cross each other at the |
Answer: Option A
Explanation:
|
| 243. |
A warner signal, which is first seen by the driver is known as |
| A. |
disc signal |
B. |
home signal |
| C. |
outer signal |
D. |
routing signal |
Answer: Option C
Explanation:
|
| 244. |
The reception signal is |
| A. |
outer signal |
B. |
home signal |
| C. |
both (a) and (b) |
D. |
none of these |
Answer: Option C
Explanation:
|
| 245. |
Which of the following statement is wrong? |
| A. |
The length of gap at crossing between two noses of a diamond crossing increases as the crossing angle decreases. |
B. |
The sand hump is a device to check the movement of a vehicle. |
| C. |
The next signal after outer signal towards station is a routing signal. |
D. |
A stop signal placed at the end of a platform is called a starter signal. |
Answer: Option C
Explanation:
|
| 246. |
An advance starter signal is used for |
| A. |
shunting |
B. |
goods train |
| C. |
loco-sheds |
D. |
all of these |
Answer: Option A
Explanation:
|
| 247. |
In a shunting signal, if the red band is horizontal, it indicates |
| A. |
stop |
B. |
proceed cautiously |
| C. |
proceed |
D. |
none of these |
Answer: Option A
Explanation:
|
Read more:
|
|