Engineering :: Irrigation Engineering
|
|
|
|
|
91. |
A side slope canal, cross-drainage works are completely eliminated. |
Answer: Option A
Explanation:
|
92. |
A contour canal |
A. |
is most suitable in hilly areas |
B. |
irrigates only on one side |
C. |
is aligned parallel to the contour of the country |
D. |
all of the above |
Answer: Option D
Explanation:
|
93. |
Which of the following is the correct sequence of the parts of a canal system? |
A. |
Head works, distributary, branch canals and minor. |
B. |
Head works, main canal, branch canal, distributary and minor. |
C. |
Head works, main canal, branch canal, minor and distributary. |
D. |
none of the above |
Answer: Option B
Explanation:
|
94. |
In a canal section, which is in partial filling and partial cutting |
A. |
the full supply level of the canal is above the natural surface level |
B. |
the bed level of the canal is below the natural surface level |
C. |
the full supply level of the canal is below the natural surface level |
D. |
the bed level of the canal is above the natural surface level |
E. |
both (a) and (b) |
|
|
Answer: Option E
Explanation:
|
95. |
The narrow strip of land left at the ground level between the inner toe of the bank and top edge of the cutting, is known as |
A. |
free board |
B. |
dowel |
C. |
inspection roadway |
D. |
berm |
Answer: Option D
Explanation:
|
96. |
The gap or margin of height, between full supply level (F.S.L.) and top of the bank is called |
A. |
free board |
B. |
dowel |
C. |
inspection roadway |
D. |
berm |
Answer: Option A
Explanation:
|
97. |
The berms when fully formed |
A. |
reduce the absorption losses and prevents leaks |
B. |
protect the bank from erosion because of wave action |
C. |
provide a scope for future widening the channel |
D. |
all of the above |
Answer: Option D
Explanation:
|
98. |
Which of the following statements is wrong? |
A. |
The top of dowel is kept above the free supply level by a margin of free board. |
B. |
The dowels are provided as a measure of safety for automobiles driven on the service roads |
C. |
The dowels act as curbs on the side of roadway towards the canal |
D. |
none of the above |
Answer: Option D
Explanation:
|
99. |
The free board in a channel is governed by the |
A. |
size of the canal |
B. |
location of the canal |
C. |
water surface fluctuations |
D. |
all of these |
Answer: Option D
Explanation:
|
100. |
The berms provide additional strength to banks and thus make it safe against breaches. |
Answer: Option A
Explanation:
|
Read more:
|
|