Engineering :: Industrial Engineering
|
|
|
|
|
|
| 171. |
Choose the correct statement. |
| A. |
CPM and PERT are event oriented techniques |
B. |
CPM and PERT are activity oriented techniques |
| C. |
CPM is an activity oriented technique while PERT is an event oriented technique |
D. |
None of the above |
Answer: Option C
Explanation:
|
| 172. |
Therblig colour for search is |
| A. |
brown |
B. |
blue |
| C. |
black |
D. |
None of the above |
Answer: Option C
Explanation:
|
| 173. |
Analysis of an operation, when carried out in terms of individual motions of a worker is known as |
| A. |
work analysis |
B. |
motion analysis |
| C. |
operation analysis |
D. |
None of the above |
Answer: Option B
Explanation:
|