Engineering :: Railway Engineering
|
|
|
|
|
|
| 41. |
A standard rail point should |
| A. |
be as strong as the other portion of the track |
B. |
have just enough rail gap between two rails |
| C. |
have the same elasticity as the other portion of the track |
D. |
all of the above |
Answer: Option D
Explanation:
|
| 42. |
In U.S.A., rails used are |
Answer: Option B
Explanation:
|
| 43. |
The joint generally not used on Indian railway is |
| A. |
supported joint |
B. |
suspended joint |
| C. |
base joint |
D. |
bridge joint |
Answer: Option D
Explanation:
|
| 44. |
Staggered rail joints are generally provided on curves. |
Answer: Option A
Explanation:
|
| 45. |
In supported rail joint, both the ends of adjoining rails are supported on a |
| A. |
single sleeper |
B. |
single fish plate |
| C. |
double sleeper |
D. |
none of these |
Answer: Option A
Explanation:
|
| 46. |
Between two rails, a gap of |
| A. |
1.5 mm to 3 mm |
B. |
3 mm to 6 mm |
| C. |
6 mm to 9 mm |
D. |
9 mm to 12 mm |
Answer: Option A
Explanation:
|
| 47. |
Two fish plates are fixed at each rail joint with eight fish bolts. |
Answer: Option B
Explanation:
|
| 48. |
No sleeper is placed just below the rail joint, as it will cause |
| A. |
more impact |
B. |
discomfort to passengers |
| C. |
either (a) or (b) |
D. |
both (a) and (b) |
Answer: Option D
Explanation:
|
| 49. |
The main purpose of welding rails is to |
| A. |
build up the worn - out parts of points and crossings |
B. |
build up the battered or worn heads of rail ends |
| C. |
to rebuild those portions of rail ends, which re burnt due to slipping of wheels at the time of applying brakes |
D. |
all of the above |
Answer: Option D
Explanation:
|
| 50. |
A welded rail joint is generally |
| A. |
supported on a sleeper |
B. |
suspended |
| C. |
supported on a metal plate |
D. |
none of these |
Answer: Option B
Explanation:
|
Read more:
|
|