Engineering :: Business Management
|
|
|
|
|
|
| |
The assumption in PERT is
|
| [A]. |
A project is always behind schedule | [B]. |
Cost of project is always more than the estimated cost
|
| [C]. |
A project can be sub-divided into a set of predictable, independent activities | [D]. |
Activities are complex in nature and time taken by them are indeterminate |
| [E]. |
None of the above |
|
|
|
|
|
|