Entry Test MCQ :: Time and Work Problems


  30 men can do a certain work in 15 days. They started working on the project but 5 of them leave after every five days. In how many days will the work be completed now?
[A]. 20 days[B]. 22 days
[C]. 25 days[D]. 18 days

Answer: Option A