Entry Test MCQ :: Time and Work Problems


  A can finish a work in 7 days B in 14 days and C in 28 days. B and C start working and are forced to leave the work after 2 days. The number of days taken by A to finish the remaining work is
[A]. 8.5 days[B]. 10 days
[C]. 5.5 days[D]. 15.5 days

Answer: Option C