M and N working separately can complete a job in 6 and 12 hours respectively. If they work for an hour alternately M starting at 10:00 AM when will the job be done?
30 men can do a certain work in 15 days. They started working on the project but 5 of them leave after every five days. In how many days will the work be completed now?